Notes on Stage 2 of renovation
Posted by mholmes on 07 Aug 2009 in Activity log, Minutes
SA goes on vacation after today, so this falls to me. This is where we seem to be at:
Before the demolition crew can remove the wall, 3 things need to happen:
- Dawn needs to walk through the space with me, and discuss where the 14+ network ports and power outlets in the wall are going to end up after the job is done
- Cable people need to come and disconnect those outlets, and pull the cables out of the way.
- Furniture and equipment needs to be moved back at least 4 feet from the wall on both sides.
SA has written to MB with regard to moving the ISE's workstations; they can presumably go to the ISE's other office space. He's also written to the History project folks about getting all their stuff out. JN and I will move all our stuff starting on Monday, some into the old coordinator's office, and some (desks/tables) into stacks far enough back from the walls; any remaining stuff from the History project can be piled up on the far side of that room.