Isolation log week 10:
Work done from home 2020-05-19 to 2020-05-22. (Four-day week)
Week 10 total hours: 29.5
G & T hours: +1.5
Tuesday 2020-05-19
0.25 hours: Update Jenkins servers.
0.25 hours: DVPP: Two of three timesheets submitted.
1.00 hours: LEMDO: Lay out H5 referencing issue and options for a decision by JJ; fix Schematron rule re part-lines; fix processing of punctuation needing to be pulled into quoted strings; add handling for gloss element; lay out duplicate gloss issue for team comments.
3.00 hours: JTEI Issue 12: Next round of proofing corrections on final article; online final pass with KT, and request for publication of last three components of the issue for RVDB.
1.75 hours: HCMC Blue Jeans meeting, and subsequent testing of Google Meet with GN.
0.25 hours: MyNDIR: Per PAB, add image count to gallery page.
1.00 hours: Francotoile: Initial work on plan for staticization (see /static in repo).
Total: 7.5 hours
Wednesday 2020-05-20
0.25 hours: Update Jenkins servers.
0.25 hours: MoEML: Prep for training session this morning.
1.00 hours: FacsViewer/ColDesp: More tweaking and testing on the possibly ill-fated issue_6 branch.
1.00 hours: MoEML: Training session on svn for new users.
2.00 hours: Scancan: Corrections to three articles per authors/editor; build and publish site.
1.00 hours: MoEML: Online training session for LS (Assistant Junior Programmer).
1.50 hours: MyNDIR: Rewrite of the index page to make it accessible as a full list and through a menu of letters.
Total: 7.00 hours
Thursday 2020-05-21
0.25 hours: Update Jenkins servers.
1.00 hours: Wendat: Rewrite processing of Latin abbreviations to collapse forms differing only in case and final period.
0.50 hours: ProD: Reading up on what's coming in ES 2020, and proposals for XSLT 4.
2.00 hours: Wendat: Lots of work on encoding of reconstructed forms; stuck on a broken Schematron rule right now.
1.00 hours: MyNDIR: Rework layout of image pages to allow experimentation with side-by-side view; fix issue with bibliography; debug issue with bad ref.
1.25 hours: Wendat: Weekly project meeting on Blue Jeans.
1.75 hours: Wendat: Split documentation into separate files, since it's now so large.
0.25 hours: Moses: Rebuild PDF, look at incoming wish-list.
Total: 8.00 hours
Friday 2020-05-22
0.25 hours: Update Jenkins servers.
0.75 hours: Wendat: [Mostly done last night] Set up new Jenkins job; fix build issues; report and explain to the team.
1.00 hours: TEI: Working on a long-standing bug in Test2 with SB. Found the problem; solution to be implemented soon.
0.50 hours: Wendat: fix image scaling bug in facs rendering; tweak to CSS.
0.50 hours: Moses: First work on a list of changes to the PDF build required by SK and ECZH.
1.25 hours: Maint: Zoom meeting with LW from sysadmin: test migration of VPN db, setup of dump script and cron job; speed testing of Loquat vs Mango.
0.50 hours: TEI: Implemented bugfix planned earlier in the day (Issue 435) and closed issue.
2.25 hours: Scancan: Encoded the whole of the final article for vol 27.
Total: 7.00 hours